Vale (VALE3; NYSE: VALE) announced on Monday (23) that it will partially resume operations at its Viga mine in Congonhas, Minas Gerais, following authorization from a state court, with the consent of the Federal Public Prosecutor’s Office (MPF) and regulatory authorities. The decision marks another step toward normalizing the mining company’s operations, which were suspended after an overflow of water and sediment in January. Vale said, however, that the resumption will not affect its iron ore production guidance for 2026.
The authorization does not amount to a full reopening of the mine. According to an order issued by Brazil’s National Mining Agency (ANM), published in the Federal Official Gazette on November 10, Vale may resume ore feeding, crushing, transportation and shipping activities, as well as construction work related to the tailings pipeline. Ore extraction from the open pit is not among the authorized activities. The agency also established a 60-day deadline for the company to meet technical requirements.
The Viga mine was shut down following an overflow on January 25, when heavy rainfall compromised drainage infrastructure. According to the MPF, at least 40 of the site’s 186 water containment structures were damaged, causing erosion, flooding and the discharge of sediment into the Maria José stream, part of the Paraopeba River basin. The incident prompted legal proceedings and a precautionary freeze of R$200 million in Vale’s assets to secure funding for environmental remediation.
Since then, Vale has carried out improvements to its drainage system, increasing the capacity of its retention basins by 64%, from 153,100 to 250,800 cubic meters, according to an MPF assessment. The partial restart remains subject to environmental and regulatory conditions, while remediation measures and independent monitoring of the site’s operational safety continue to be discussed.
For Vale, the decision eases operational restrictions but does not, for now, represent an expansion of production capacity. The company has not disclosed how much ore it will be able to process or ship during this phase, nor has it provided a timeline for the full resumption of mining activities. With production targets unchanged, the immediate impact of the decision is primarily regulatory: Vale is making progress in restoring operations, but a complete return to normal activity at Viga remains subject to regulatory approval.